Show, don’t tell.

These are the artifacts I build and run on real programs, rebuilt as sanitized samples. The structures are mine; project names and details are illustrative, and the adoption figures are the public OPNAV-GPT numbers.

Portfolio management

Portfolio health board

Projects roll up to programs and programs to the portfolio. Leadership reads one line per initiative: health, phase, the next decision needed, and open dependencies.

Illustrative sample
Initiative Program Phase Health Next decision Deps
Secure AI assistant rollout Enterprise AI Light the path On track Approve SIPR onboarding wave 3 4
Repository migration to SharePoint Online Platform modernization Draw the lines Watch Confirm retention labels with records officer 6
Service desk modernization (JSM) Service operations Hold the orbit On track Accept SLA dashboard 2
Knowledge base restructure Knowledge management Map the sky At risk Name a content owner per space 3
Event platform requirements Program operations Draw the lines On track Sign off on the requirements baseline 1

Adoption metrics

Adoption dashboard: OPNAV-GPT

Adoption tracked like delivery: by network, by wave, and by what users can reach. Public figures, rounded down.

Public figures
Pilot
250+
NIPR users
3,500+
SIPR users
3,700+
Total users
7,200+
3,900+knowledge assets available to OPNAV-GPT users
55+enterprise data sources supporting secure AI use
50+reusable prompts in the OPNAV-GPT library
10+cross-functional workstreams coordinated as delivery lead

Prioritization

WSJF scoring

Weighted Shortest Job First: cost of delay (business value + time criticality + risk reduction) divided by job size. The highest score goes first, and the scoring makes tradeoffs explicit for a prioritization discussion.

Illustrative sample
Feature Business value Time criticality Risk reduction Cost of delay Job size WSJF
Single sign-on for secure-network users 13 13 8 34 5 6.8
Prompt library, version 2 8 5 3 16 3 5.3
Records retention labels 5 8 13 26 8 3.3
Usage analytics dashboard 8 3 5 16 5 3.2

Governance

RAID log

Risks, assumptions, issues, and dependencies, each with an owner, a response, and a status reviewed weekly.

Illustrative sample
ID Type Description Owner Response Status
R-01 Risk Account provisioning on the secure network takes longer than the onboarding window Platform lead Pre-stage accounts one wave ahead; track in Jira At risk
A-02 Assumption Content owners will review migrated libraries within two weeks Delivery lead Confirm in writing at kickoff; escalate at day 10 Watch
I-03 Issue Training sessions conflict with a command exercise Adoption lead Record sessions; add office hours the following week On track
D-04 Dependency Security accreditation update before the next release Cyber team Weekly sync; release gate in Jira Watch

Ownership

RACI matrix

One accountable owner per activity. Most stalled decisions trace back to two.

Activity Sponsor Delivery lead Platform team Data owners Adoption lead
Prioritize the backlog A R C C C
Configure workflows and permissions I A R C I
Approve data sources I C C A/R I
Training and communications I A C I R
Release go / no-go A R C C C

R responsible · A accountable · C consulted · I informed

Risk

Risk heat map

Likelihood × impact. Anything in the top-right gets an owner and a dated response this week.

Likelihood 15

Vertical axis: impact 1 to 5. R1 provisioning delays · R2 accreditation timing · R3 content owner availability · R4 training conflicts.

Jira

JQL behind leadership dashboards

Leadership reporting should come straight from the board, not a separate spreadsheet. These filters power the gadgets I build for sponsors and program leads.

Working JQL

Overdue work leadership should see

project in (DLV, PLAT) AND statusCategory != Done
  AND duedate < now() ORDER BY priority DESC, duedate ASC

Blocked items and who they wait on

project = DLV AND (status = Blocked OR "Flagged" is not EMPTY)
  ORDER BY updated ASC

Adoption stories in the current increment

project = DLV AND labels = adoption
  AND sprint in openSprints() ORDER BY rank

Aging service requests past SLA

project = HELP AND "Time to resolution" = breached()
  AND resolution = Unresolved ORDER BY created ASC

Executive reporting

One-page status pack

Decisions first, then risks, then progress. A sponsor should know what is needed from them in the first ten seconds.

Illustrative sample

Decisions needed this week

  • Approve onboarding wave 3 for secure-network users (sponsor)
  • Name a content owner for each knowledge space (division leads)

Top risks

  • Account provisioning lead time exceeds the onboarding window. Response: pre-stage one wave ahead.

Progress

Wave 2 complete. Training attendance at target. Prompt library expanded; usage analytics dashboard in build.

Next two weeks

Wave 3 onboarding, retention label sign-off, and the 30-day adoption check for wave 2.

About this website

Direct contact. Useful resources.

This site shares my experience, illustrative work samples, and free resources. Downloads are available without signup. Inquiry forms prepare an email to aerikaasaxe@gmail.com; you send it from your own email application.

No automatic Jira ticket, SharePoint record, newsletter subscription, or Confluence publishing integration is represented by this version.

Work with me

Discuss an engagement

A short questionnaire helps me prepare for our first conversation. It takes about three minutes.

Stay in touch through Field Notes

Read lessons from federal delivery work and email me if you would like to hear about future resources.

Email me about Field Notes

Opens your email application. Send your message there to request updates; this site does not automatically subscribe you.